Vestas signs 90 MW purchase agreement

With reference to company announcement No. 44/2012 of 20 November 2012, Vestas confirms the signature of a firm and unconditional purchase agreement for the Talinay Oriente project in Chile.

Additional information about the project:

Customer: Enel Group
Project name: Talinay Oriente wind power plant
Location/Country: Chile (Limari province)
Number of MW: 90 MW
Number of turbines/turbine types: 30 x V90-2.0 MW and 15 x V100-2.0 MW
Contract type: Turnkey contract
Contract scope: Supply, installation, civil and electrical works and a three-year service and maintenance agreement (AOM 400).
Time of commissioning: The project is expected to be commissioned in Q1 2013.