Source : Vestas Website

Vestas has received a firm and unconditional order for 41 V100-1.8 MW turbines for South Africa.

Aarhus, Denmark, 2012-12-21 08:38 CET (GLOBE NEWSWIRE) —  

Additional information about the project: 

Customer: At the customer’s request, further details about the customer cannot be disclosed.
Project name: At the customer’s request, further details about the project cannot be disclosed.
Location/Country: South Africa
Number of MW: 73.8 MW
Number of turbines/turbine type: 41 x V100-1.8 MW turbines
Contract type:   Supply-and-installation
Contract scope: The contract includes supply, installation and commissioning of the wind turbines, a VestasOnline® Business SCADA solution, as well as a 15-year full-scope service agreement (AOM 5000).
Time of delivery: Delivery of the turbines is planned for the fourth quarter of 2013 and the wind power plant is expected to be commissioned by February 2014.